Epic Test Design Index
Updated 2026-09-13 against main 083974c27f3a21a15807dd248bb6bc4fe04a5cd8. Eight plans cover all 99 stories from the approved current epics decomposition (25 historically done, 74 backlog). Plans are not acceptance or execution evidence; the numbering revision does not change a tested commit or fabricate a new run.
| Epic | Story count | Plan |
|---|---|---|
| 1 — REST → MCP foundation | 16 | Regression and remaining evidence |
| 2 — OpenAPI import | 15 | Storage, refs, HTTP contract, preview and re-import |
| 3 — MCP catalog | 20 | Protocol adapters, Tools, Resources and Prompts |
| 4 — Background execution | 10 | Durable Tasks, fencing and recovery |
| 5 — Observability | 13 | Correlation, GlitchTip, spool, metrics and SLO |
| 6 — Load testing | 6 | Safety plans, runner, stop and reports |
| 7 — Deployment | 9 | Offline installation, migrations, backup and restore |
| 8 — Release qualification | 10 | Immutable RC, matrices, soak and publication gate |
Shared authority: system architecture testability, current QA inventory and execution strategy, approved PRD and epic acceptance criteria. Historical handoff/baseline artifacts are not current pass evidence.
Current plans use the approved sequential IDs: Epic 2 2.1–2.15, Epic 3 3.1–3.20, Epic 4 4.1–4.10 and Epic 5 5.1–5.13. The old→new mapping and AC allocation are recorded in the corresponding plan tables. Archived execution records retain their original identifiers; no new test execution is implied by renumbering.
Development boundary
ATDD should freeze a finite, story-scoped AC-to-test checklist before implementation, reuse existing tests and matching completed checklists, and avoid regenerating tests in review. A green existing behavior must not be deliberately broken to fake RED. Qualification work runs only at its owning milestone; updating these plans does not reopen completed stories or launch any workload.
The project now configures pre-implementation ATDD through _bmad/custom/bmad-build-auto.toml. The TEA plugin remains enabled; only its stock post-dev ATDD injection is disabled in .bmad-loop/policy.toml. Test artifacts are seeded into new worktrees. Mandatory acceptance scaffolds must be activated and pass before story completion; skipped scaffolds are not executed RED evidence. This is workflow configuration, not evidence of a completed live loop run; existing runs were not modified.